Improvement/Rehabilitation of Level III Water Supply System

  • Category: 2017
  • Published: Monday, 09 July 2018 15:50
  • Written by Editor1
  • Hits: 109

Republic of the Philippines

Province of Laguna

MUNICIPALITY OF LILIW

CONTRACT AGREEMENT

                                          This Contract Agreement made on this 20th day of February, 2018 at Liliw, Laguna by and between

                                                      the Municipal Government of Liliw, represented herein by the Hon. Municipal Mayor ERICSON J. SULIBIT, with office                                                    address at Gat Tayaw Strett, Liliw, Laguna,as the PARTY OF THE FIRST PART, hereinafter called the "ENTITY", duly                                                          authorized for this purpose,

    and

                                                       TTAI General Construction, with office address at Block 3 lot 3 Hanna St., Villa Quintana Subdivision, San Agustin                                                       (Poblacion) Trece Martires City Cavite, represented herein by JAYNER AMBITO, Authorized Representative, who has been                                                   authorized for this purpose as the PARTY OF THE SECOND PART, hereinafter called the "CONTRACTOR".

                                               Whereas, the ENTITY is desirous that the CONTRACTOR execute the Works, viz, Improvement/Rehabilitation of Level III                                            Water Supply System at Brgy. Luquin, this Municipality herein called the Works and ENTITY has accepted the Calculated Bid of                                            the CONTRACTOR for the execution and completion of the Works at the calculated unit bid process shown in the attached Bill of                                          Quantities on a total Contract Price of Four Million Thirty thousand Eight Hundred Seventy Two Pesos & 0/100                                                                 (Php4,030,872.50) Philippine pesos.

                                              WHEREAS, the whole WORKS in this PROJECT as covered by this CONTRACT shall be completed within One Hundred Fifty                                           (150) calendar days in accordance with the provisions of the said documents.

                                             The items of work covered under this contact are enumerated hereunder:

                                      ITEM NO.    PARTICULARS                                    QTY   UNIT          UNIT PRICE               TOTAL AMOUNT

                                            1         UPVC pipe 8"x6m Class 150                   144     pcs           12,436.50                   1,790,856.00

                                            2        UPVC pipe 8"x90                                      12     pcs          24,140.50                       289,686.00

                                            3        UPVC pipe 8"x45                                      10     pcs          13,131.00                       131,310.00

                                            4        UPVC PIPE 6"X90                                       6     PCS          8,450.50                          50,703.00

                                            5        UPVC pipe 4"x6m Class-150                         5     pcs          2,938.00                          14,690.00

                                            6       UPVC pipe 6"x6m Class-150                          5     pcs          6,221.50                           31,107.50

                                            7       Gibault 8"                                                 12      pcs          4,693.00                           56,316.00

                                            8       Gibaut 6"                                                   4       pcs          3,128.50                           12,514.00

                                            9       CI Gate Valve 8" M/M                                  4       pcs         37,504.00                         150,016.00

                                          10       CI Gate Valve 6" M/M                                  2       pcs          23,521.00                          47,042.00

                                          11       GI Nipple 4"x12" Std S 40                            4        pcs              929.00                            3,716.00

                                          12       GI Elbow 4"x90 Sd                                      4        pcs            1,104.50                           4,418.00

                                          13       GI St Elbow 4" Std                                      4        pcs            1,708.50                           6,834.00

                                          14       CI Saddle Clamp 8"x1/2"                             3        pcs             1,096.50                           3,289.50

                                          15       CI Saddle Clamp 6"x 1/2"                            2         pcs               821.50                          1, 643.00

                                          16       Deformed bar 12mm                               380         pcs                210.00                         79,800.00

                                          17       Deformed bar 10mm                                200         pcs               146.50                         29,300.00

                                         18        GI Wire #16                                             30          kls                  71.50                          2,145.00

                                         19        GI Wire #12                                             15          kls                  93.50                           1,402.50

                                         20       CW nail                                                     20          kls                  99.00                           1,980.00

                                         21       Plywood 1/2"                                             28          pcs                726.00                         20,328.00

                                         22      Plywood 1/4"                                              16          pcs                330.00                           5,280.00

                                         23      Coco Lumber 2"x2"x12"                              150         pcs                 198.00                         29,700.00

                                         25      Sahara Cement                                          130        bags                  33.00                           4,290.00

                                         26     Cement                                                     400         bags                245.50                          98,200.00

                                         27     Sand                                                           60         cu.m.               715.00                         42,900.00

                                        28      Gravel 3/4"                                                  80          cu.m.            1,265.00                       101,200.00

                                        29      Air Release Valve 1"                                       1           unit             11,136.50                        11,136.50

                                        30     Flow Meter 8" ARAD BRAND                             1           unit            200,909.50                      200,909.50

                                        31    Steel Wire Rope 1/2"                                    250           m                       96.00                        24,000.00

                                        32    Steel Wire Rope 3/8"                                    200           m                       66.00                        13,200.00

                                        33    Steel Wire Rope Clip 1/2"                              120          pcs                      48.00                          5,760.00

                                        34    Steel Wire Rope Clip 3/8"                              100          pcs                      36.00                          3,600.00

                                               1LOT INDIRECT COST                                                                     722,000.00                       722,000.00

                                               Grand Total -                                                                        Php                                         4,030,872.50

                              NOW, THIS CONTRACT AGREEMENT WITNESSETH AS FOLLOWS:

                              1. In this Contract Agreement, words and expressions shall have the same meanings as are respectively assigned t them in the                                             Conditions of Contract herein referred to.

                              2. The following documents are hereby incorporated to made an integral part of this Contract Agreement.

                                  a. The said procurement in the form of bidding procurement accomplished and submitted by the Contractor including (i) the Bid                                              prices in the Bill of Quantities (ii) the Construction Schedule (iii) the Manpower Schedule (iv) the Equipment Utilization Schedule                                          (v) the Cash flow and Payment Schedule and (vi) the Affidavit of Site Inspection

                                  b. The conditions of the Contract

                                  c. The Drawings

                                  d. The specifications

                                  e. The Bill of Quantities in the Said Form of Bid

                                  f. Bid Security

                                  g. The Performance of the Contractor

                            3. In consideration to the payment to be made by the ENTITY to the CONTRACTOR as hereinafter mentioned, the CONTRACTOR hereby                                 covenants with the ENTITY to execute, complete and maintain the works and remedy any defects therein in conformity in all respect                                   with the provisions of this Contract Agreement. The Contract Completion time is One hundred Fifty (150) working days.

                            4. The ENTITY  hereby covenants to pay the CONTRACTOR in consideration of the execution, completion and maintenance of the works                                  at the works of the said bid prices stated in the said Form of Bid involving the estimated amount of Four Million Thirty Thousand                                          Eight Hundred Seventy Two Pesos & 50/100 (Php4,030,872.50) in the same manner as prescribed by this Contract Agreement. After                                  signing of this contract, the ENTITY shall pay the CONTRACTOR the mobilization and demobilization costs. The succeeding payment                                    shall be based on project progress accomplishment billing.

                            5. The Implementing Rules and Regulations of RA 9184 regarding the payment of liquidated damages shall applied in this Contract.

                            6. The Contractor shall comply with and strictly observe all laws regarding workmen's healthy and safety, workmen's welfare,                                                  compensation for injuries, minimum wages,hours of labor and other laws.

                            7. The contractor's agrees to hire at least 50% of the unskilled and 30% of the skilled labor requirements to be taken from the available                                  bonafide residents in this municipality in which the project is to be undertaken and penalizing those who fail to do so per Republic Act                                  6685.

                            8. The Contractor's Covenants and agrees to undertake all works incidental tp the completion of the project.

                            9. All other provisions of RA 9184 shall be applied to this Contract. In witness whereof, the parties have caused their respective                                             signature to be hereunto affixed on the day and year first above written.

                           Signed, sealed, delivered by Hon. Ericson J. Sulibit, the Municipal Mayor (for the Entity)

                           Signed, sealed ,delivered by Mr. Jayner Ambito, the Authorized Representative (for the Contractor)

                           SGD. Binding Signature of PROCURING ENTITY

                           SGD. Binding Signature of CONTRACTOR

                           Republic of the Phlippines)

                           Province of Laguna          )

                          Municipality of Sta. Cruz    )

                                                                           A C K N O W L E D GE M E N T 

                                  BEFORE ME, NOTARY PUBLIC for and in the Municipality of Liliw, Laguna personally appeared ERICSON J. SULIBIT with                                           Government Employee ID No. 1011-001 at his official capacity as the Mayor of Municipality of Liliw, Laguna representing the Republic of                             the Philippines and TTAI General Construction, represented by Jayner Ambito with SSS No. 33-14187144 known to me and to me known                             to be the same person who executed the foregoing CONTRACT AGREEMENT and they acknowledge to that the same as their true act and                           deed for in and behalf of the PARTIES they represent.

                                 This instrument consist of three pages including this page on which the acknowledgement is written duly signed by the contracting                             parties and their witnesses at the bottom of pages two of the instrument and on the left margin of the other pages.

                                IN WITNESS WHEREOF, I have hereunto fixed my signature and seal this 20th day of February, 2018.

                                                                                                                       SGD. ATTY. ANTONIO P. RELOVA

                                                                                                                               Notary Public

                                                                                                                              Until December 31, 2019

                                                                                                                              PTR No. 5740060

                                                                                                                             January 4, 2018 LAGUNA